Why Change Orders Destroy Margins and How Contracts Should Handle Them

In brief

A change order usually loses money because it is priced as the cost of the added work, while the real cost also includes pricing time, extra trade trips, schedule days and rework of finished work. A worked example shows a change that looks like a $600 gain turning into a $650 loss. Unwritten field extras are worse. Contracts protect margin by fixing the pricing method, the time impact, the signers and the cutoff dates before the first change is requested.

Change orders in construction destroy margins when they are priced as the cost of the added work alone. The contract fixes that by setting the pricing method, the time impact and the people allowed to sign before the first change is ever requested.

Why change orders in construction cost more than the line item

A change order is a written agreement that alters the scope, price or schedule of a signed construction contract. The owner moves a wall, upgrades a window package or adds an outlet, and the builder prices the added work.

The trouble is what the price usually covers. Most change orders are built from the trade quote and the material invoice, with a markup added on top. That captures the direct cost. It misses the cost of handling the change, which is spread across people and days that nobody bills.

Four costs ride along with almost every change:

  • Pricing and paperwork. A project manager collects quotes, writes the change, gets it signed, updates the budget and issues new purchase orders.
  • Extra trade trips. A trade that has already finished on a house has to send a truck and a crew for a single item.
  • Schedule days. Every day a change adds to a build carries site overhead, supervision, insurance and financing on the house.
  • Rework of finished work. A change after drywall means cutting, patching and repainting work that was already paid for.

Each one is small. Together they often exceed the markup, which is why a builder can approve a dozen fairly priced changes and still watch the job margin shrink.

A worked example: how a fairly priced change order loses money

The figures below are an example built from stated assumptions, not data from any job. They are a reasonable starting point for running the same math on your own numbers.

Assume an owner asks for an added interior wall with two outlets after drywall is hung. The trade quotes and materials come to $4,000. The builder adds a 15 percent markup and bills $4,600, so the change shows $600 of gross profit on paper.

Now count the costs the price left out:

Cost the line item missed Assumption Cost
PM and superintendent time to price, order and reschedule 6 hours at a $60 loaded hourly rate $360
Extra electrician trip for one item one trip charge $250
Schedule days added to the build 3 days at $80 a day of site overhead and financing $240
Cutting and patching finished drywall and paint one patch scope $400
Total handling cost $1,250

The change that looked like a $600 gain is a $650 loss ($600 minus $1,250).

Priced correctly, the cost base is $5,250 ($4,000 plus $1,250). At the same 15 percent markup, the change should have been billed at about $6,040.

Scale it to the whole house. Assume a $350,000 contract with a planned profit of $42,000, a 12 percent margin. The owner signs five changes like this one, billed at $23,000 in total. On paper, the job should earn $45,000 on $373,000 of revenue, about 12.1 percent. Counting the handling costs, it earns $38,750, about 10.4 percent. About 1.7 points of margin disappear on changes that every report showed as profitable.

The change order nobody wrote down

The most expensive construction change order is the one that never becomes paper. A superintendent standing in a house is asked whether the framer can add blocking for a heavier fixture, or whether the plumber can move a drain six inches. Saying yes keeps the house moving, and the trade does the work.

Weeks later the trade sends an invoice for the extra. The work was never priced or signed, so the builder has nothing to bill the owner for. If three of those extras run $800 each in this example, $2,400 comes straight out of profit with no matching revenue.

These field extras are hard to see because they hide inside trade invoices. They appear as small overruns across many cost codes instead of as one line labeled "change." The Project Manager Layer post describes how this starts: when a PM cannot be reached, the person standing in the house says yes, and the cost shows up as a change order nobody priced.

In Michigan there is a second reason to put every change on paper. Michigan Administrative Code R 338.1533(1) requires that all agreements and changes to agreements between a residential builder or contractor and the customer be in writing and signed by the parties, with copies provided to the customer. An unwritten change to a homeowner contract is both hard to collect and out of step with the licensing rules.

Change order clauses every construction contract should have

The time to settle how a change will be priced is before anyone wants one. Once the owner is waiting on an answer and the trade is standing in the house, every term is a negotiation.

These clauses are a reasonable starting point for a residential or light commercial contract. This is general information, not legal advice; have an attorney review contract language before you use it.

  1. Written authorization before work. No changed work starts until a change order is signed by the people named in the contract. Emergencies that affect safety or code compliance can be handled with a written field directive and priced within a set number of days.
  2. A fixed pricing method. State how changes are priced: direct cost plus a stated markup percentage for overhead and profit, with the same method applying to credits.
  3. A handling charge. Add a flat administrative charge per change order, or a minimum change order amount, so pricing time and extra trips are covered even on small items.
  4. A time impact line. Every change order states the days it adds to the schedule. A change signed with no time line leaves the original completion date in force.
  5. Cutoff dates by stage. Selections and layout changes close at named stages, such as before framing inspection or before drywall. Later changes are priced at a higher markup or declined.
  6. Payment terms. Changes are paid when signed or with the next draw, so the builder does not finance the owner's upgrades until closing.
  7. A process for disputed changes. When the parties agree a change is needed but not on the price, the work can proceed under a directive while cost records settle the number. The widely used AIA A201 general conditions call this a construction change directive.

The same terms flow down to trade contracts. A trade gets paid for extra work only with a written field order signed by the PM, and the trade contract says so. That one line stops most of the unwritten extras described in the section above. The Crews or Subs post covers how trade agreements and company crews differ in cost; the field order rule applies to both.

Who can approve a change order

Every change order clause depends on knowing who may sign. Name them in the contract on both sides.

On the owner's side, name one person, or two people who must both sign. A spouse or partner who first sees an upgrade at the final walk is likely to dispute it.

On the builder's side, the project manager prices and signs changes within a written dollar limit, and anything above it goes to operations. Superintendents report requested changes and do not approve them. That split keeps the person under schedule pressure from trading margin for speed, the same reason the quality control post gives for having a second person audit the work.

How to track change order management across many jobs

A builder running one house can track changes in a folder. A builder running thirty needs a few measures reviewed every week.

  • Change orders signed before the work started, as a share of all changes. This is the measure to watch first. Anything signed after the work is a negotiation from a weak position.
  • Change order dollars as a share of the original contract, by house. Track your own trend. A rising share points to unclear plans, weak selections or an owner who needs a cutoff conversation.
  • Days from request to signature. Long waits stall trades and invite verbal approvals.
  • Unbilled extras found at closeout. Compare trade invoices to signed changes when each house closes. Every mismatch is a field extra that skipped the process.

Review the numbers by superintendent and by trade. If one superintendent's houses carry most of the unbilled extras, the issue is the approval habit on that site. If one trade keeps invoicing extras, its scope sheet is probably missing detail.

Common Questions

What is a change order in construction?

A change order in construction is a written, signed agreement that modifies a contract after it is signed. It records the added or deleted work, the change in price and the change in schedule, and it becomes part of the contract.

Who pays for change orders in construction?

It depends on who caused the change. Owner requested upgrades and design changes are usually paid by the owner. Changes caused by the builder's own errors are usually absorbed by the builder, and the contract should say how unforeseen conditions such as buried debris are handled.

What is a deductive change order in construction?

A deductive change order removes work from the contract and reduces the price. The credit should be the cost of the deleted work minus anything already bought or installed, priced with the same method the contract uses for added work.

Can a contractor refuse a change order?

It depends on the contract. Under forms such as AIA A201, the owner can direct a change and the contractor proceeds while price and time are settled. Work far outside the original scope is generally treated as a new agreement. An attorney should review the specific contract language.

How do you reduce change orders in construction?

Finish selections and plans before the contract is signed, set cutoff dates by stage, price handling costs into every change and require signatures before work starts. Owners make fewer late changes when the price of a late change is clear.